Clemson University
Generator Replacement
Provided initial study in 2015 and is now redesigning the service entrance to comply with the findings of the initial generator study of the Biosystems Research Complex building for Clemson University’s main campus:  Four (4) 600KW parallel generators will be used rather than a single generator. This option includes the replacing the existing padmount transformer with new one and relocating in order to place a new 3,000 Amp automatic transfer switch and paralleling switchgear where the present transformer is located.